Periodic inspection and testing of internal wiring
installations is necessary. Internal wiring should be checked every year for
safe operations.
While carrying out inspection and testing of internal wiring
installations, following points should be checked: Incoming Service Line Connection
Check and ensure the following:
1. Service
line coming in to the premises is properly terminated and brought in
2. Check for
fuse wire rating on each of the phases so as to ensure it is of correct rating
3. Check for
wire sizes to be of correct size to carry the required current
4. Check for
earthing to be properly maintained at the service line side
Main Switch Board
A main switch board exists at the point of termination of
service line. Supply is provided through this board in to the premises.
1. Ensure
that the main switch board is closer to the point of supply in the premises
2. Check for
fuses / circuit breakers used of adequate sizes for all phases
3. Check for
correct ON/OFF working of Main Switch. A main switch plays a very important
role as it helps to switch off the complete supply of the premises in case of
emergency / repairs. It should always be in good working condition.
Check for any mechanical faults in switching operations that
might cause it to remain continuously in ON state. This may be problematic in
emergency cases when the electrician wants to switch the supply off
4. Ensure
that the Switch board assembly is well covered to protect against rain /
weather conditions
5. Inspect
to see that you are clearly able to trace the neutral and earthing wires in
different colour
6. Inspect
the electricity meter connections are properly fastened
Internal Wiring Circuits
Internal Wiring Circuits are to be checked for following
points:
1. Ensure
that each circuit branching out of Main Switch board has a connected load of
not more than 800 watts or 10 points
2. Test for
Insulation resistance of conductor and earth to be as per IEC specifications
3. Electrical
resistance from connection with Earth electrode should not be more than one ohm
4. Ensure
metallic covering of iron clad switches, distribution boards are properly
earthed
5. Test that
that leakage current is less than 1/5,000 of maximum supply current.
Key Tests to be performed for Wiring Installations
1. Insulation
Resistance Test:
In this test, the insulation resistance of a wire is tested
to ensure that there is no leakage current flowing through it. As per IE rules,
the insulation resistance between wiring and earth should not exceed 1/5,000 of
the current flowing through it.
The test is performed using “Megger” instrument. In this,
main switch is put in OFF condition and all the lighting connections on the
circuit are short circuited. The Megger is connected between line and the
earth. Megger is then rotated to generate voltage and then the reading on the
dial of Megger is noted
The insulation resistance should not be less than 50
Mega-ohm divided by no. of circuits. The insulation resistance per circuit is
calculated as 50 Mohm. If the result value is more than 1 then it should be
considered as 1 mega-ohm. In no case this value should be less than 0.5 mega
ohm.
2. Earth
Continuity Test:
This is second most important test for safety of
installation.
All metal clad switches, metal parts, covers, conduits must
be solidly connected to earth. In absence of this, there could be a severe
damage to the whole electrical installation, appliances connected to it. In
adverse events, the leakage current flowing through it may cause severe
electrical shock to the person coming in physical contact with it.
In order to test this, the main switch should be in open
position. All other circuit contacts like bulbs and switches should be ON
position. The Earth continuity tester is then connected between the switch /
conduit and an independent earth. The tester will indicate the value of
resistance. In all cases the value should not exceed more than 1 ohm. If the
value appears higher than 1 ohm it indicates that the switch / conduit is not
properly earthed.









